The developer behind the trouble-plagued Midwater apartment tower project on the Gold Coast has confirmed contractors are on the site and it will be completed after the head builder walked away from the project over a pay dispute.
CITY BEAT Chris Herde 2 min read November 7, 2024 - 1:00AM
Courier Mail
Don't miss out on the headlines from Business. Followed categories will be added to My News.follow
Almost two months after the builder of a $100m apartment tower on the Gold Coast walked off the job, the developer of the troubled Midwater project says it will now be completed, giving long suffering buyer some hope.
York Property Holdings says it’s appointed a new team to oversee the completion of the 39-storey tower after Tomkins Commercial pulled the pin in September over a payment dispute.
York – which is part of the Heran Group – says the new contractor will complete the structure and external facade.